Project initiation date   September 2019 Project complication date   September 2020
Credit source Tabriz Municipality
Partner companies in project implementation Khatam al-Anbia Camp (Ashura Institute)
The project output Modification of trenches and implementation of liners as well as shotcrete of cells 2 and 3, after 14 months from the start of operation

Supply of UF and NF filters for the treatment plant for 3 months

 

Brief description of the project
Tabriz municipal waste Landfill was designed as five landfill cells and equipped with leachate conduction manholes in a 50-hectare land. The operation of cell number one has started on 22/4/2013 and its capacity is coming to end. Cells 2 and 3 are under construction and cell 4 and hospital waste cell are being excavated. The above landfill is equipped with the most modern leachate treatment plant with the MBR method and with a capacity of 200 cubic meters per day. The surrounding area is afforested with an area of 25 hectares. This project aims to properly manage the final disposal of waste over energy extraction and recycling and to minimize the environmental hazards of leachate and municipal waste disposal.